LCD Setting

After pressing and holding ENTER button for 3 seconds, the unit will enter setting mode. Press "UP" or "DOWN"
button to select setting programs. And then, press "ENTER" button to confirm the selection or ESC button to
exit.

Setting Programs:

Program
Description
00
Exit setting mode
Output source priority:
01
To configure load power
source priority
Maximum charging current:
To configure total charging
current for solar and utility
02
chargers.
(Max. charging current =
utility charging current +
solar charging current)
Selectable option
Escape
Solar first
Utility first (default)
SBU priority
10A (Only available for
1K/4K/5K models)
30A
15
Solar energy provides power to the
loads as first priority.
If solar energy is not sufficient to
power all connected loads, battery
energy will supply power the loads
at the same time.
Utility provides power to the loads
only when any one condition
happens:
- Solar energy is not available
- Battery voltage drops to low-level
warning voltage or the setting
point in program 12.
Utility will provide power to the
loads as first priority.
Solar and battery energy will
provide power to the loads only
when utility power is not available.
Solar energy provides power to the
loads as first priority.
If solar energy is not sufficient to
power all connected loads, battery
energy will supply power to the
loads at the same time.
Utility provides power to the loads
only when battery voltage drops to
either low-level warning voltage or
the setting point in program 12.
20A