Daikin RXYQ5PY1 Service Manual: Placing The Unit

Daikin r-410a heat pump 50hz/60hz cooling only 50hz.
Hide thumbs

Advertisement

SiEN34-705
3.5

Placing the Unit

! Make sure the unit is installed level on a sufficiently strong base to prevent vibration and
! The base should be bigger around than the width of the unit's legs (66 mm), and should
! The height of the base should be at least 150mm from the floor.
! Secure the unit to its base using foundation bolts. (Use four commercially
! The foundation bolts should be inserted 20 mm.
Note:
! There are restrictions on the refrigerant pipe connecting order between outdoor unit in the
! When installing on a roof, make sure the roof floor is strong enough and be sure to water-
! Make sure the area around the machine drains properly by setting up drainage grooves
Installation Manual
noise. (Refer to figure 7)
support the unit. (Refer to figure 8)
If protective rubber is to be attached, attach it to the whole face of the base.
available M12-type foundation bolts, nuts, and washers.)
In the case of 8HP type or more, the
product cannot be supported with
four corners.
In the case of 5HP type, the product
can be supported with four corners.
5HP type
8 · 10HP type
12 · 14 · 16 · 18HP type
case of the multi system.
See the Note in "1-2-1 Combination" for detail.
proof all work.
around the foundation.
Drain water is sometimes discharged from the outdoor unit when it is running.
Heat Pump / Cooling Only 50Hz (RX(Y)Q5~54P)
figure 7
Foundation bolt point (φ15 dia. : 4 positions)
A
B
figure 8
Model
A
635
930
1240
It is need in the case of 8HP type or more
Center of the product
It is need in the case of 8HP type or more
Center of the product
Depth of product
B
497
792
1102
225

Advertisement

   Related Manuals for Daikin RXYQ5PY1

Comments to this Manuals

Symbols: 0
Latest comments:
  • GMacD Dec 22, 2015 11:58:
    Your website is crap in providing useful informatio​n on your products.