Daikin RXYQ5PY1 Service Manual: Piping Installation Point

Daikin r-410a heat pump 50hz/60hz cooling only 50hz.
Hide thumbs

Advertisement

Appendix
7.2

Piping Installation Point

Since there is a possibility that oil may be collected on a stop machine side, install piping
between outdoor units to go to level or go up to an outdoor unit, and to make a slope.
The projection part between multi connection piping kits
When the piping length between the multi connection kits or between multi connection kit and
outdoor unit is 2m or more, prepare a vertical projection part (200mm or more as shown below) only
on the gas pipe line location less than 2m from multi connection kit.
In the case of 2m or less
In the case of 2m or more
130
Connection
Kit A
Less than 2m
Vertical
Projection
Less than 2m
5m or less
than 5m
Connection
Kit B
Less than 2m
Vertical
Projection
200mm or
more
2m or more
Vertical
Projection
Less than 2m
Maximum length from a connection
kit. 10m or less from first branch.
(Equivalent Piping Length 13m)
(V3037)
General Information
SiEN34-705
(V3036)
(V3038)

Advertisement

   Related Manuals for Daikin RXYQ5PY1

Comments to this Manuals

Symbols: 0
Latest comments:
  • GMacD Dec 22, 2015 11:58:
    Your website is crap in providing useful informatio​n on your products.