16
Commissioning
Figure 9: Battery Configuration Switches
Quick Start: DC Charge Controller for Honeywell Wind Turbine WT6500 - Rev 2.0 - 29Nov11
1.
To configure the DC Charge Controller to a 48 VDC system (refer to figure 9) set
switch S1 to "On".
2.
Set switch S2 to "On".
3.
Set switch S3 to either "On" if using AGM batteries, or "Off" is using flooded batteries
(refer to figure 9).
4.
Turn on the following switches in the following sequence:
•
Battery switch
•
DC Charge Controller ON/OFF switch
•
15 Amp fused disconnect
•
DCCC junction box ON/OFF switch
5.
Verify turbine LED on DC Charge Controller is green.
EXPLOSION OR FIRE HAZARD
Entering battery information incorrectly may result in
explosion or fire.
Quick Start