OUTDOOR INSTALLATION

For heaters located outdoors, using the built-in stackless venting system.
Risk of explosion if a unit burning propane gas is installed in a pit or other low spot. Propane is heavier than air. Do not
install the heater using propane in pits or other locations where gas might collect. Consult your local building code officials to
determine installation requirements and specific installation restrictions of the heater relative to propane storage tanks and
filling equipment. Installation must meet the requirements for the Standard for the Storage and Handling of Liquid Petroleum
Gases, ANSI/NFPA 58 (latest edition) in the U.S., or CAN/CSA B149.2 (latest edition) in Canada. Consult local codes and fire
protection authorities about specific installation restrictions.
Locate the heater on a level surface in an open area that is protected from drainage or run-off.
Install the heater in an area where leaves or other debris will not collect on or around the heater.
To avoid damage to the electronic components in the heater, take care to prevent prolonged exposure
to driving sources of water (such as lawn sprinklers, heavy roof runoff, hoses, etc.). Avoid operation
in persistent, extreme, moist or salty environments.
In extreme weather, shut down the heater and disconnect the power to it until the weather has
moderated. In areas subject to hurricanes or very high winds, purchase the Bolt Down Bracket Kit,
P/N 460738.
HEATER CLEARANCES – OUTDOOR
• In an outdoor installation it is important to ensure water is diverted
from overhanging eves with a proper gutter/drainage system. The heater
must be set on a level foundation for proper drainage.
• This unit shall not be operated outdoors at temperatures below -20
If the heater is located under a roof or deck overhang, there must be at least
three feet (1M) of clearance between the bottom of the overhang and the top of
the heater exhaust vent, see
overhang, the space around the heater must be open on three sides.
For minimum exhaust vent clearances for building openings, see
page 17.
In Canada, the heater must be installed with the top of the vent at least 10 feet
(3M) below, or to either side of, any opening into a building.
Orient the heater for convenient access to the water connections and the gas
and electrical connections.
Install the heater at least 18 in. (45 cm) from any property line.
If installing the heater next to or near an air conditioning unit or a heat
pump, allow a minimum of 36 in. between the air conditioning unit
and the heater.
P/N 472592
(U.S. and Canada)
WARNING
IMPORTANT!
Figure
8. If the heater is under a roof or deck
CAUTION
Section 3. Installation
o
F.
3 ft. (1 M) or more
Figure 9,
For Heater mounting
bolts and clamps,
purchase separately
Bolt Down Bracket Kit,
Part No. 460738.
Lead
Anchor
Figure 8.
Rev. C 10-5-07

Hide quick links:

Advertisement

Table of Contents
loading

This manual is also suitable for:

400k btu/hr asme200k btu/hr250k btu/hr hd300k btu/hr

Table of Contents