3.2.1

Earthquake-proofing construction method

This section explains how to mount each unit by using the earthquake-proofing
construction method.
(1) Anchoring to floor surfaces
Anchoring items need to be prepared separately to install the unit using this method.
*1
Bolt length must be specified.
*** = Bolt length (mm)
The bolt length (mm) varies depending on the building structure. Consult
with your Fujitsu engineer.
U41631-J-Z816-5-76
Leveling foot
(Floor)
Figure 3.1 Earthquake-proofing construction method

(anchoring on the floor surface)

3.2 Earthquake Preparedness Measures
N-C230-4130-X514
N-C230-4080-X003
N-F6-WB12-121
N-F6-WM12-121
N-F6-B12-***121
(*1)