6 Start-up and Check-out

1. Make sure the system is free of leaks and that air is
purged from the system.
CAUTION
Fix any leaks found before proceeding further.
Leakage from the boiler piping can result in severe
damage to the boiler.
2. Many soldering fluxes contain Zinc Chloride which can
cause severe corrosion damage to stainless steel. After
completing all domestic water connections, flush the
indirect water heater thoroughly before leaving the
installation. This is particularly important if the indirect
water heater will be unused for an extended period of
time after installation. Flush the indirect water heater by
drawing at least three times its volume from the tank.
3. Make sure that all electrical connections are made
correctly and that no exposed high voltage wiring is
present.
4. Make sure that each zone valve or circulator operates
when, and only when, its thermostat calls for heat. Let
each zone operate long enough to purge any remaining
air from the system.
5. Set the indirect water heater to the desired
temperature. Because hot water presents a scald
hazard, it is best to set the thermostat at 120°F or lower
and raise it only if necessary to provide adequate hot
water.
6. Re-enable the burner and allow the boiler to operate.
Make sure that the boiler shuts down when the indirect
water heater is satisfied.
1 8 |
Indirect Fired Water Heaters Installation and Operating Manual

Hide quick links:

Advertisement

Table of Contents
loading

This manual is also suitable for:

Sst250-65Sst300-80Sst450-119

Table of Contents