Normal Sequence of Operation
Power Up
The normal power up sequence is as follows:
115 VAC power applied to furnace.
Integrated control module performs internal checks.
Integrated control module flashes LED one time.
Integrated control module monitors safety circuits
continuously.
Furnace awaits call from thermostat.
Heating Mode
The normal operational sequence in heating mode is as
follows:
R and W thermostat contacts close, initiating a call
for heat.
Integrated control module performs safety circuit
checks.
Induced draft blower is energized causing pressure
switch contacts to close. Humidifier terminals are en-
ergized with induced draft blower.
Igniter warm up begins upon close of pressure switch
contacts.
Gas valve opens at end of igniter warm up period,
delivering gas to burners and establishing flame.
Integrated control module monitors flame presence.
Gas valve will remain open only if flame is sensed.
Circulator blower is energized on heat speed follow-
ing a fixed thirty second blower on delay. Electronic
air cleaner terminals are energized with circulator
blower.
Furnace runs, integrated control module monitors
safety circuits continuously.
R and W thermostat contacts open, completing the
call for heat.
Gas valve closes, extinguishing flame.
Induced draft blower is de-energized following a fif-
teen second post purge. Humidifier terminals are de-
energized.
Circulator blower is de-energized following a select-
able heat off delay period (60, 90, 120, or 180 sec-
onds). Electronic air cleaner terminals are de-ener-
gized.
Furnace awaits next call from thermostat.

SYSTEM OPERATION

Cooling Mode
The normal operational sequence in cooling mode is as
follows:
Fan Only Mode
The normal operational sequence in fan only mode is as
follows:
R and Y thermostat contacts close, initiating a call
for cool.
Integrated control module performs safety circuit
checks.
Outdoor fan and compressor are energized.
Circulator blower is energized on cool speed follow-
ing a fixed five second on delay. Electronic air cleaner
terminals are energized with circulator blower.
Furnace circulator blower and outdoor cooling unit
run, integrated control module monitors safety cir-
cuits continuously.
R and Y thermostat contacts open, completing the
call for cool.
Outdoor fan and compressor are de-energized.
Circulator blower is de-energized following a fixed
forty five second cool off delay period. Electronic air
cleaner terminals are de-energized.
Furnace awaits next call from thermostat.
R and G thermostat contacts close, initiating a call
for fan.
Integrated control module performs safety circuit
checks.
Circulator blower is energized on cool speed. Elec-
tronic air cleaner terminals are energized.
Circulator blower runs, integrated control module
monitors safety circuits continuously.
R and G thermostat contacts open, completing the
call for fan.
Circulator blower is de-energized. Electronic air
cleaner terminals are de-energized.
Furnace awaits next call from thermostat.