<When the AC power is off (The power cords are not plugged into the outlet)>
Connect the power cords to NEC Express5800/ft series in the following order:
(1) Connect the power cord to the AC inlet B (for Group1)
(2) Connect the power cord to the AC inlet A (for Group2)
(3) Confirm that the POWER switch of the PCI module for Group1 is illuminated.
(4) Make sure that the two BMC Status LEDs for PCI modules (for Group1/for Group2) are
turned off.
IMPORTANT:
Linux for NEC Express5800/ft series. Otherwise the setup may not be performed
properly.
Preparation is now completed. Start the installation of Linux for NEC Express5800/ft series.
<When the AC power is on (The power cord is plugged to the wall outlet and the main unit's
power is off)>
(1) Check the LED of the PCI module's POWER switch.
If the PCI module for Group1's POWER switch is lit, the PCI module for Group1 is
primary. Preparations are complete. Start the installation of Linux for NEC
Express5800/ft series.
If the PCI module for Group2's POWER switch is lit, the PCI module for Group1 is
secondary. Continue to (2). Make PCI module for Group1 the primary module.
Rack-mount model (Rear)
If the BMC Status LED is red and blinking, do not start installing