Power Up Sequence

Supply Power and Power Up the System

Dell Force10 recommends re-inspecting your system prior to powering up.
Verify that:
The equipment is properly secured to the rack and properly grounded.
The equipment rack is properly mounted and grounded.
The ambient temperature around the unit (which may be higher than the
room temperature) is within the limits specified for the Z9000.
There is sufficient airflow around the unit.
The input circuits are correctly sized for the loads and that sufficient
overcurrent protection devices are used.
All protective covers are in place.
NOTE: A US AC power cable is included in the shipping container for powering
up an AC power supply. All other power cables must be ordered separately.
CAUTION: Electrostatic discharge (ESD) damage can occur if components
are mishandled. Always wear an ESD-preventive wrist or heel ground strap
when handling the Z9000 and its components.
When the chassis powers up, the fans come on at high speed. The fan speed
slows as the system boots up.
The SYS LED does not light up until the boot-up sequence is complete. When
the boot-up is complete, the SYS LED is steadily lit green.
AC Power
Connect the plug to each AC power connector, making sure that the power cord
is secure.
As soon as the cable is connected between the Z9000 and the power source, the
chassis is powered-up; there is no on/off switch.
DC Power
To connect the plug to the DC power connector, follow the steps below:
Installing the Hardware