24
General Information
Unit Leveling
Follow the instructions outlined
below and illustrated in Figure 11 to
determined whether or not the
chiller is set level.
1. Measure an equal distance up
from each foot of the chiller
(identified as X in Figure 11) and
make a punch mark at each
measured distance.
2. Suspend a clear plastic tube along
the length of the chiller as shown
in Figure 11.
Figure 11 – Checking Unit Levelness
Raise chiller at one
end to align match
marks with water
level.
Clear Plastic Tube
(Fill tube with water to punch mark.)
3. Fill the tube with water until the
level aligns with the punch mark at
one end of the chiller; then check
the water level at the opposite
mark.
If the water level does not align
with the punch mark, use full-
length shims to raise one end of
the chiller until the water level at
each end of the tube aligns with
the punch marks at both ends of
the chiller
4. Once the unit is level across its
length, repeat Steps 1 through 3 to
see if unit is level across the width.
5. If isolation pads have been used,
shim the center support.
Measure and mark
an equal distance
up from each
chiller foot.
CDHF-SVN01B-EN