Fujitsu PRIMECENTER M1 19-inch Rack User Manual page 90

Rack system for primergy, primequest, bs2000, storage
Table of Contents

Advertisement

Power Distribution
7.3.5.1
Installation options for 700 mm wide asymmetrical racks
Rack height
Installation direction vertically
42 HU
ok
24 HU
ok
Table 13: Installation options for 700 mm wide asymmetrical racks
Performing the task
Ê Install two PDU brackets as described on
Figure 57: Single-phase 8-way 10 A socket strip mounted in a 700 mm wide asymmetrical rack
Ê Screw the socket strip with 2 screws onto the PDU brackets.
90
Installation direction horizontally
Max. 4x with PDU kit 3 HU
Max. 4x with PDU kit 3 HU
page
69.

Advertisement

Table of Contents
loading

Table of Contents