Case Pressure Purge Switch
1. Per Section 4-2e on page 4-13, re-
move securing hardware from elec-
tronics assembly and lay on bench.
2. Disconnect the two electrical termi-
nals, note location.
4-16
Maintenance and Troubleshooting
Case Pressure Purge
Switch 903690
The bracket does not have to be removed from the electronics assembly for this procedure.
Figure 4-14.
Case Pressure Purge Switch Installation
Model NGA2000 HFID
3. Disconnect tube at pressure switch.
4. Remove mounting screws (2) and
washers (2).
Reverse procedure for installation of re-
placement switch.