Connecting the Management Interface
DETAILED STEPS
Take the Ethernet cable provided (with attached RJ-45 connector) and plug it into the desired MNG port
Step 1
on the front panel of the SCE 2000 , as shown in the following figure.
Figure 5-2
1
2
Connect the other end of the Ethernet cable into your management network.
Step 2
Make sure that you push on the RJ-45 connector attached to the cable until you hear a click, which
indicates that the connector is fully inserted and secured in the receptacle. Gently pull on the plug to
confirm whether the plug is locked into the socket.
If the Link LED on the SCE 2000 management port does not light, try removing the cable and reinserting
it firmly into the module socket. To disconnect the plug from the socket, press down on the raised portion
on top of the plug, releasing the latch. You should hear an audible click indicating the latch has released.
Carefully pull the plug out of the socket.
If the management port Link LED on the SCE 2000 still does not light, verify that the cable is connected
correctly to the appropriate network element on its second end.

How to Verify Management Interface Connectivity

If the SCE 2000 platform has been powered up, test now to verify that connectivity has been established
between the SCE 2000 and the remote management host. If the SCE 2000 platform is not powered up,
perform this step after starting the SCE 2000 platform.
SUMMARY STEPS
1.
2.
Cisco SCE 2000 4xGBE Installation and Configuration Guide
5-26
Chapter 5
Cabling the Management Port
PW R A
PW R B
STA TU S
BY PAS S
MN G 1
MN G 2
CO NS OL
E
LIN K RX
LIN K/
AU X
10/1 00/
ACT IVE
LIN K/
100 0
10/1 00/
ACT IVE
100 0
RX
MM
SU B
3
If only one management port is used — connect the port directly to the LAN.
If both management ports are used — connect both ports to the LAN via a switch.
After you connect the cable to the appropriate Mng port and to your network, check the relevant Mng
port LEDS.
Test connectivity. From the host that you intend to use for remote management, ping to the SCE
2000 by typing ping and the SCE 2000 IP address, and pressing Enter (see the example, below).
Connecting the Management Interfaces and Performing Initial System Configuration
C is co S
C E 2 0 0 0
Se rie s
4 xG B E
TX
LIN K RX
TX
LIN K RX
TX
LIN K RX
TX
TX
RX
MM
TX
RX
MM
TX
RX
MM
GB E-1
TX
LIN E
NE T
GB E-2
SU B LIN
E/C AS CA
DE NE T
OL-7824-06

Hide quick links:

Advertisement

Table of Contents
loading

This manual is also suitable for:

Sge2000Slm2024t-naSce 2000 4xgbe

Table of Contents