Site Preparation Checklist
Also be aware of the following caution concerning the use of Category 5e and Category 6 Ethernet
cables:
Caution
Category 5e and Category 6 cables can store large levels of static electricity because of the dielectric
properties of the materials used in their construction. Always ground the cables (especially in new cable
runs) to a suitable and safe earth ground before connecting them to the module.
Site Preparation Checklist
Table 2-4
series switch. Completing each activity helps ensure a successful switch installation.
Table 2-4
Site Planning Checklist
Task No.
Planning Activity
1
Space evaluation:
•
Space and layout
•
Floor covering
Impact and vibration
•
Lighting
•
Maintenance access
•
2
Environmental evaluation:
Ambient temperature
•
•
Humidity
•
Altitude
Atmospheric contamination
•
Airflow
•
3
Power evaluation:
Input power type
•
Power receptacles (Depends on power supply)
•
•
Receptacle proximity to the equipment
•
Dedicated (separate) circuits for redundant
power supplies
•
UPS for power failures
DC systems: Proper gauge wire and lugs
•
4
Grounding evaluation:
Circuit breaker size
•
CO ground (AC- and DC-powered systems)
•
Catalyst 6500 Series Switches Installation Guide
2-22
lists the site planning activities that you should perform prior to installing the Catalyst 6500
Verified By Time
1
Chapter 2
Preparing for Installation
Date
OL-5781-04