Installation Instructions

Power-On Self Test

Once the Director 2/140 is connected to a power source, a Power-On Self Test (POST)
is initiated. The following sequence of events occur during the POST:
1. Amber LEDs on both CTP cards and all FPM cards illuminate momentarily.
2. The green LED on each CTP card (active and backup) lights as the card is tested
and FPM cards are tested.
3. Green LEDs associated with Fibre Channel ports sequentially illuminate as the
ports are tested.
After successful POST completion, the green power LED on the front bezel, green
LED on the active CTP card, and green PWR OK LEDs on both power supplies
remain illuminated.
If a POST error or other malfunction occurs, refer to the "Maintenance Analysis
Procedures" section in the hp StorageWorks director 2/140 service manual.

Further Setup

For additional information on installing and configuring the Director 2/140, please see
the hp StorageWorks director 2/140 installation guide.