NOTE:
In storage nodes that reboot after the patch installation, if volumes were online, then the volumes
will resync before the patch installation can complete successfully. This resync could take a while
depending on the amount of data that was written while the storage node was rebooting.
NOTE:
The cluster may continue flashing the warning symbol while the volumes are resyncing. Clicking
on the cluster resolves the blinking.
6.
After the patch is successfully installed, log in to each storage node in the management group
and navigate to the TCP/IP Network tab window. You should see two 10GigE devices on the
TCP/IP tab.
Configure the 10 GbE ports for SAN/iQ software communication using the
CMC
For each storage node in the cluster, configure the ports as follows:
1.
Right-click the existing bond and delete it. (This is the old ALB bond of the two 1 GbE interfaces.)
2.
Search for the storage node using the Find dialog in the CMC.
3.
Log in to the management group (if necessary).
4.
Make sure the storage node status is Normal before proceeding.
5.
On the TCP/IP tab window, right-click the eth2 interface and select Edit.
6.
In the Edit TCP/IP Configuration window, select one of the following options to assign an IP ad-
dress:
• Obtain an IP address automatically using the DHCP/BOOTP protocol
• Obtain a static IP Address, and manually assign an available IP address
If you are prompted with the following message, click OK to continue. The condition described
is not actually true.