Installing the Switch
In this publication, the term Catalyst 6500 series refers only to the switch chassis listed in Chapter 1.
Note
The Catalyst 6000 series switches (Catalyst 6006 and Catalyst 6009 switches) are described in a
separate publication, the Catalyst 6000 Series Switch Installation Guide.
This chapter describes how to install a Catalyst 6500 series switch. The chapter is divided into sections
that cover installing the different Catalyst 6500 series chassis. Pointers within the overall chassis
installation procedures point to separate installation procedures that cover installing various components
and assemblies. The process of installing the switch can be broken down into a series of tasks. These
tasks are listed in
Table 3-1
Task
Unpacking the switch
Installing the switch
Connecting the chassis to system
ground
Installing and cabling the power
supply or supplies
Cabling the supervisor engine
and modules to the network
Powering up the chassis
OL-5781-08
Table
3-1.
Catalyst 6500 Series Switch Installation Process
Description
Remove the switch from the packaging materials.
We recommend that you save the packaging material for use
Note
later if you need to move the chassis.
All Catalyst 6500 series chassis can be rack-mounted. Some chassis
offer the option of installation as a freestanding unit through the use
of rubber feet or stabilizer brackets.
Construct and attach a system ground wire from the building (earth)
ground to the system ground point on the chassis.
Normally, one power supply is shipped installed in the chassis. The
second power supply, if part of the switch configuration, is shipped
separately. You now install the second power supply and connect the
power supplies to source power, either AC or DC.
The various ports on the supervisor engine and on the modules that
are installed in the chassis must be connected to the network. This
process can involve only attaching a network interface cable to the
module port, or it can include the installation of a transceiver of
some type in the supervisor engine or module port, and then
attaching the network interface cable to the transceiver.
After completing the network cabling and making sure that system
ground is connected, the power supplies can be turned on. The
system powers up and runs through a set of built-in diagnostics.
3
C H A P T E R
Catalyst 6500 Series Switches Installation Guide