This guide highlights the new and unique process for commissioning. For installation, please refer to the detailed steps in the Installation & Service Instructions.
Heating circuit
DHW temperature
System pressure
DHW ECO function
Reduced temperature level
Wifi connection
Service menu
Fault display
Burner status
OK > confirm settings
Menu > opens the main menu
Up & down > change parameter
On the following pages you will find a step by step guide to commission the product by using the control panel. The default parameters are highlighted for each step. Please refer to the last page of this document to receive more information.
Access Point AP
Indicates the boiler is ready to be set up press 4 seconds to start commissioning from the panel
C.4 Operating Mode
4 > weather comp., 13 - default > constant operation (switch live) with optional room thermostat
End
After completing the last step the arrow will appear indicating commissioning is complete, press OK to confirm the setting and start the flue gas sensor check. The boiler will restart.
Adv
Select Adv and confirm with OK to access advanced parameters and make further adjustments.
FST will appear (the boiler is carrying out flue gas sensor check & will fire for a few seconds to raise sensor temperature). Please wait for this to complete. Once completed the boiler set temperature will appear on the screen and boiler is ready to run.
C.7 Gas Type
2 - default > natural gas, 3 > liquid gas, press OK to confirm the setting
C.8 Flue System Type
1 > room air dependent (60 mm), 2 - default > room sealed (60 mm / 100 mm),
3 > room air dependent (80 mm), 4 > room sealed (80 mm / 125 mm), press OK to confirm the setting
C.9 Flue System Length
press to adjust the length in metres - the default setting is 1 m (an additional length of 1 m must be factored in for every flue bend), press OK to confirm the setting
End
After completing the last step the arrow will appear indicating commissioning is complete, press OK to confirm the setting and start the flue gas sensor check. The boiler will restart.
FST will appear (the boiler is carrying out flue gas sensor check & will fire for a few seconds to raise sensor temperature). Please wait for this to complete. Once completed the boiler set temperature will appear on the screen and boiler is ready to run.
The application can be the Google Play Store
For further information scan the QR code:
The Viessmann Account is our single sign on for all of our applications. Once set up you will get access to all our tools including ViGuide & our PartnerPortal. To sign up for a Viessmann Account, simply scan the QR code or visit www.viessmann.co.uk/account. It will take you directly to the application form. Once processed you will receive an email. Please confirm your settings in order to verify your account.
Once your Viessmann Account is set up, you can access the Partner Portal via the QR code:
If further information is needed visit our support page. Here you will find detailed explanations, FAQs & video tutorials. Just scan the QR code to access the page
or visit viessmann.co.uk/vitodensgetstarted
Phone: 01952 675000
Email: info-uk@viessmann.com
Here you can download full pdf version of manual, it may contain additional safety instructions, warranty information, FCC rules, etc.
Advertisement
Need help?
Do you have a question about the 100-W HEAT ONLY and is the answer not in the manual?
Questions and answers