Summary of Contents for TMG TMG-DT3061

  • Page 1 www.tmgindustrial.com 0/24 TOLL FREE:1-877-761-2819...
  • Page 2: Main Specifications

    MAIN SPECIFICATIONS : • Assembly size : W9.15 x L18 x H6 (m) / 30 x 59 x 19.7 (ft) Ridge height : 6m / 19.7 ft • Peak clearance : 5.4m / 17.7 ft • • Front and back door : 4.27 x 3.96 (m) / 14 x 13 (ft) •...
  • Page 3 The layout of foundation(two).  Note: the ground anchor is installed on the cement block. Depth of cement Unit: mm (ft) www.tmgindustrial.com 2/24 TOLL FREE:1-877-761-2819...
  • Page 4 Baseplate layout. • PRIOR TO ASSEMBLY Please read the instructions carefully before installation. It is very important to follow your local safety regulations and industry standards during installation. Regulations may include but are not limited t o : • Safety helmets, protective eyewear, and clothing. •...
  • Page 5 FRAME STRUCTURE DIAGRAM. www.tmgindustrial.com 4/24 TOLL FREE:1-877-761-2819...
  • Page 6 TMG-DT3061 PART LIST PARTS GRAPHICAL DESCRIPTION LENGTH CODE Peak arch tube L2570mm (for 5 middle trusses ) Peak arch tube L2570mm (for front and rear trusses) Upper rafter tube L2921mm (for middle trusses) Upper rafter tube L2921mm (for front and rear trusses)
  • Page 7 W260xL480mm Baseplates for middle truss Ratchets φ16x150mm Expansion bolts Ceiling cross bar L2083mm (front and rear trusses) Ceiling cross bar L2233mm (front and rear trusses) Side door left tube L2027mm Side door right tube L2027mm Side door L2005xW925mm Front and rear vertical door L1984mm rail (left side upper part)
  • Page 8 Side door upper tube L1980mm Bottom tension bar L1970mm (front and rear trusses) Bottom tension bar L815mm Front and rear door hand L1984mm winch crossing tube L1993mm Top cover tension tube Top cover tension tube L700mm Front and rear roll up door L2195mm dropping tubes (to connect #16)
  • Page 9 Right pulley system for front L150mm and rear doors Left pulley system for front L150mm and rear doors Front and rear vertical door L240mm rail connection plate Front and rear vertical door L220mm rail end plate (floatable to keep door rail straight) φ32mm Tension tube end water plug φ48mm...
  • Page 10 STEP 1 : BASEPLATE POSITIONING AND INSTALLATION. • Installation diagram of expansion bolt. PART PART www.tmgindustrial.com 9/24 TOLL FREE:1-877-761-2819...
  • Page 11 STEP 2 : ASSEMBLE ALL TRUSSES. Front and rear trusses. • PART PART 24x2 www.tmgindustrial.com 10/24 TOLL FREE:1-877-761-2819...
  • Page 12 Middle trusses. (5 trusses) • PART PART 24x5 www.tmgindustrial.com 11/24 TOLL FREE:1-877-761-2819...
  • Page 13 Lay down all (7) trusses on the ground when the assembly is all completed and before moving to next step, • and then wrap (#38) around the sharp points of the joint to avoid friction between the fabric and the interface, resulting in fabric damage.
  • Page 14 STEP 3 : PUT UP THE FRONT TRUSS. (IT IS SUGGESTED TO USE CRANE FOR HOISTING) PART www.tmgindustrial.com 13/24 TOLL FREE:1-877-761-2819...
  • Page 15 STEP 4 : PUT UP THE REST TRUSSES. • Refer to step 3 to put up the rest trusses, connect all purlins (#5) with bolt (#28) and secure all bolts firmly on each span before going to next truss . PART PART www.tmgindustrial.com...
  • Page 16 Repeat above step to put up all other trusses (from 3rd to 7th truss), and connect all purlins. • PART PART www.tmgindustrial.com 15/24 TOLL FREE:1-877-761-2819...
  • Page 17 Tension cable installation . All cables are diagonally installed on each side of the interval. • PART PART www.tmgindustrial.com 16/24 TOLL FREE:1-877-761-2819...
  • Page 18 STEP 5 : FRONT AND REAR TRUSSES TO COMPLETE. (2 TRUSSES) PART PART www.tmgindustrial.com 17/24 TOLL FREE:1-877-761-2819...
  • Page 19 32x2 STEP 6 : INSTALL FRONT AND REAR COVER PANELS. • Lift up (#34) cover panel, starting from the center point of the frame (highest ridge point) use ropes (#32) through the grommets to tie the panel to the truss firmly. All grommets need to be tied to the frame as shown.
  • Page 20 Install the front and rear door pressing plate. • PART 52x2 www.tmgindustrial.com 19/24 TOLL FREE:1-877-761-2819...
  • Page 21 STEP 7 : INSTALL MECHANICAL ROLL UP DOORS. • Door curtain installation. PART PART www.tmgindustrial.com 20/24 TOLL FREE:1-877-761-2819...
  • Page 22 Front and rear door installation, please look at the door from inside. • • The hand winch (#23) comes with a shorter cable, we call it cable (#B). PART PART www.tmgindustrial.com 21/24 TOLL FREE:1-877-761-2819...
  • Page 23 STEP 8 : INSTALL ROOF COVER. NOTE: The cover must be installed on a windless day. DO NOT attempt to install the cover during windy • conditions. PART www.tmgindustrial.com 22/24 TOLL FREE:1-877-761-2819...
  • Page 24 After the cover is installed on the roof, insert the plastic pipe (#37) slowly into the grooves on two ends of the • cover (not two sides), and then insert tension tubes (#14,#14A) in the groove on both sides of the cover bottom, Add the water plug (#25) on the 1st tube (#14) to protect the fabric while the tube is going through and add the water plug on the last tube also to keep water away.
  • Page 25: After The Installation

    AFTER THE INSTALLATION. Walk around and inspect the building periodically to make sure all components are still firmly secured and the whole building is well supported. Check all bolts and nuts as well as all connection points to make sure they are all in good position.