Removing And Installing System Components; Removing The Chassis From The Equipment Rack - Cisco 12416 Replacement Instructions Manual

Chassis replacement instructions
Table of Contents

Advertisement

Removing and Installing the Chassis

Removing and Installing System Components

To remove and install system components from one chassis to another, follow these steps:
Remove the blower modules and then install them into the replacement chassis. Refer to the
Step 1
Cisco 12016, Cisco 12416, and Cisco 12816 Router Installation and Configuration Guide for detailed
procedures.
Remove the power supplies and the power shelf and then install them into the replacement chassis. Refer
Step 2
to the Cisco 12016, Cisco 12416, and Cisco 12816 Router Installation and Configuration Guide for
detailed procedures.
Step 3
Remove the cards from all three card cages and then install them into the replacement chassis.

Removing the Chassis from the Equipment Rack

This section provides the following procedures:
Detaching the Supplemental Bonding and Grounding Connection
If your router has supplemental bonding and grounding cables attached to any of the earth ground cable
receptacles on the chassis, you must detach these cable lugs from the chassis before you can remove the
chassis from the equipment rack. Two receptacles are located on the front flanges of the chassis, near the
lower corners of the switch fabric card cage (see
power interface panel on the back of the chassis (see
To detach a supplemental bonding and grounding cable lug from the chassis, use
a reference and follow these steps:
Step 1
Remove the two bolts, washers, and nuts that secure the bonding and grounding cable lug to the chassis.
Save the mounting hardware, because you will use it in a later procedure.
Remove the bonding and grounding cable and set it aside.
Step 2
Repeat
Cisco 12016, Cisco 12416, and Cisco 12816 Router Chassis Replacement Instructions
12
For the RP, refer to the RP installation and configuration note for detailed procedures.
For line cards, refer to the line card installation and configuration note for detailed procedures.
For CSCs, SFCs, and the alarm card, refer to the Cisco 12016, Cisco 12416, and Cisco 12816 Router
Installation and Configuration Guide for detailed procedures.
Detaching the Supplemental Bonding and Grounding Connection, page 12
Removing the Chassis from the Equipment Rack, page 13
Step 1
and
Step 2
for a second supplemental bonding and grounding connector (if present).
Figure
3) and two receptacles are located on top of the
Figure
4).
Figure 3
or
Figure 4
as