Step 5
Install calibrator assembly onto the display support, tighten 3
screws by using bit T6 torque driver with 3.0 lbs-in.
Front USB flex cable and earth cable assembly
Place the USB Assembly Front (N1913-68305) at position
shown. Install screw (0515-5114) and tighten using Bit T6
torque driver with 3 lbf.in
Place the Assembly Bracket at the position shown.
Sequence for USB Assembly Front Earth Cable Installation:
1) Earth Cable N1912-61018
2) Flat Washer 3050-2633
3) Screw 0515-5114
Tighten using Bit T6 torque driver with 3 lbf.in
Ensure the cable lug is touching the solder lead as shown.