WARNING: To reduce the risk of personal injury from hot surfaces, allow the drives and the internal system components
WARNING:
to cool before touching them.
Prerequisites
Prerequisites
Before you perform this procedure make sure that you have a small flat-bladed, nonconductive tool available.
Procedure
Procedure
1. Power down the server.
2. Remove all power:
a. Disconnect each power cord from the power source.
b. Disconnect each power cord from the server.
3. Disconnect all peripheral cables from the server.
4. Do one of the following:
If the server is in tower mode: Position the tower server for hardware configuration.
If the server is in rack mode: Remove the server from the rack .
5. Remove the front bezel .
6. Remove the access panel .
7. If installed, remove the air baffle .
8. Remove the energy pack.
9. Access the bottom of the server and push the latches inwards to release the holders.
10. Remove the energy pack holders.
HPE ProLiant ML30 Gen10 Server Maintenance and Service Guide