SOFTENER INSTALLATION AND USER GUIDE
RETURN TO NORMAL MODE
BARRIE • ONTARIO • CANADA TF: 705.733.8900 WWW.EXCALIBURWATER.COM
Step 5SSA: ‐ Adjust the unit add point in GPM as specified on the
specifications of the system model. Press NEXT to go to Step 6SS.
Step 6SS: ‐ Set the regeneration to start "IMMEDIATE" when the
capacity falls below reserve.
Step 7SS: ‐ Set the maximum number of days to be "14" between
regenerations.