Method 1: Short PIN2 and PIN3 of Remote port first,
then press the metal button switch. The battery pack
will start to work within 25 seconds. If there is no
communication input, after 5 minutes it will stop to
function.
Method 2: Install a switch between PIN1 and PIN2 on
the Remote port. When the switch is turned on, the
battery pack will start to work within 25 seconds. If
there is no communication input, after 5 minutes it will
stop to function.
Item.
Description
1
Remote portl
2
PIN1 of Remote port
3
PIN2 of Remote port
4
PIN3 of Remote port
5.2 Switching on/off the AEG energy storage system
Switching on: open the door, and turn on the switches
of Load/Grid/Battery/Remote.
Turn off: Open the door, and turn off the switches of
Load/Grid/Battery/Remote.
Please refer to the below picture to locate the position
of the switches:
AEG LOW VOLTAGE ENERGY STORAGE UNIT (8 KWH / 12 KWH) INSTALLATION MANUAL
Item.
Description
1
PV switch
2
Grid breaker
3
Load breaker (remark: back-up load)
4
GEN breaker
5
Battery breaker
6
Remote switch
5.3 Operating the LCD touchscreen
LCD position
Item.
Description
1
Touchscreen LCD panel
5.3.1 General remarks
Through the LCD display you will be able to monitor
the functioning of your AEG energy storage system and
adjust its settings. The LCD display gives you access to
a menu consisting of different sections, each featuring
sub-menus.
Some of the advanced settings need to be carried out
necessarily by the installer. These are explained in
detail in „5.4 Adjusting the settings - for installers only".
Some settings require the input of a password. The
default password is „12345".
When a sub-menu or a function requires the input of a
password, the following interface will be displayed:
21
EN
PD202107 V1-21