Figure 33. Installing a cassette in the 9040-MR9 system
Preparing the 9040-MR9 system for operation after permanently removing a PCIe
adapter
To prepare the system for operation after permanently removing a PCIe adapter, complete the steps in
this procedure.
Procedure
1. Ensure that you have the electrostatic discharge (ESD) wrist strap on and that the ESD clip is plugged
into a ground jack or connected to an unpainted metal surface. If not, do so now.
2. Choose from the following options:
• If you completed the procedure with the system power turned off, continue with step "3" on page
47.
• If you completed the procedure with the system power turned on, continue with step "4" on page
48.
3. Using your labels, reconnect the power cords (A) to the system unit as shown in the following figure.
Fasten the power cords to the system by using the hook-and-loop fasteners (B) as shown in the
following figure.
Installing, removing, and replacing PCIe adapters in the 9040-MR9 system 47

Advertisement

Table of Contents
loading
Need help?

Need help?

Do you have a question about the Power System System E950 and is the answer not in the manual?

Questions and answers

Subscribe to Our Youtube Channel

This manual is also suitable for:

Power system 9040-mr9

Table of Contents