Keys To A Successful Installation
If not installed correctly by qualified personnel, the brewer will not operate properly and damage may result.
Damage resulting from improper installation is not covered by the warranty.
Here are the key points to consider before installation:
Electrical:
All FETCO brewers require NEUTRAL. Ground is not an acceptable substitute. Installation without neutral
may cause damage to the electronic components.
The wiring diagram is located in this manual and on the inside of the cover.
120 volt units are supplied with appropriate cords and plugs for 15 amp or 20 amp service.
Dual voltage units (120/208-240VAC) are not supplied with a cord or plug. Consult local codes to
determine if a cord and plug can be installed, or if the unit must be hard wired
The installation must comply with applicable federal, state, and local codes having jurisdiction at your
location. Check with your local inspectors to determine which codes will apply.
Plumbing:
This equipment is to be installed to comply with the applicable federal, state, or local plumbing codes.
The water line must be flushed thoroughly prior to connecting it to the brewer to prevent debris from
contaminating the machine.
Verify that the water line will provide at least ¾ gallon per minute before connecting it to the brewer.
General:
Utilize only qualified beverage equipment service technicians for installation. A Service Company Directory
may be found on our web site, http://www.fetco.com.
Make sure the brewer is level by adjusting the feet.
Installation Instructions
Brewer Setup
1. Review the Dimensions for the unit you are installing. Verify that the brewer will fit in the space intended for it,
and that the counter or table will support the total weight of the brewer and dispensers when filled.
2. Place the brewer on the counter or stand.
3. When the brewer is in position, level it front to back as well as side to side by adjusting the feet.
4. Remove the back cover to access the electrical connections and control board.
Water Connection
1. Water inlet is a ¼ inch male flare fitting.
2. The brewer can be connected to a cold or hot water line. Cold water is preferred for best coffee flavor, but hot
water will allow for faster recovery times.
3. Install a water shut off valve near the brewer to facilitate service. If an in-line water filter is used, it should be
installed after the water shut off valve and in a position to facilitate filter replacement.
4. Flush the water supply line and filter before connecting it to the brewer.
5. Verify that the water line will provide at least ¾ gallon per minute and that the water pressure is between 20
and 75 psig.
Electrical Connection
1. Verify that the actual voltage at the electrical service connection is compatible with the specifications on the
brewer's serial number label. Make sure the electrical service includes neutral.
2. The temperature and water tank fill level are pre-set at the factory. There is no need to turn off the heaters
during the installation process. The heaters are disabled by the control board until the tank is full of water. The
heating process will start automatically when the tank has filled.
3. A fused disconnect switch or circuit breaker on the incoming power line must be conveniently located near the
brewer, and its location and markings known to the operators.
4. The body of the brewer must be grounded to a suitable building ground.
A ground lug is provided in the brewer next to the terminal block. Use
only 10 gauge copper wire for grounding.

Installation

(For Qualified Service Technicians Only)
4
Warning: To prevent
electrical shock, this
unit must be properly
grounded.