ABB ZS1 Instruction Manual page 21

Air-insulated medium voltage switchgear, 12 kv/17.5 kv

Advertisement

• Store the panels upright.
• Do not stack panels.
• Panels with basic packaging:
– Open the packaging, at least partially.
• Panels without packaging:
– Loosely cover with protective sheeting.
– Ensure that there is sufficient air circulation.
• Check regularly for any condensation until the
start of installation.
2. Panels with seaworthy or similar packaging with
internal protective sheeting:
• Store the transport units:
– protected from the weather,
– in a dry place,
– safe from damage.
• Check the packaging for damage.
• Check the drying agent (see also section 4.2):
– on arrival of the consignment,
– later at regular intervals.
• When the maximum storage period, starting
from the date of packaging, has been
exceeded:
– the protective function of the packaging
can no longer be guaranteed,
– take suitable action if intermediate storage
is to continue.
Note:
Do not walk on the roof of the panels (rupture
points in pressure relief devices)!
ø 35
Figure 4/1: Handling by crane
1.5
Lifting lug
1.18 Marking on the centre of gravity
22
60°
1.5
1.18
ABB Power Distribution