Operating Power

2.2 Operating Power
WARNING: RISK OF ELECTRICAL SHOCK AND EQUIPMENT DAMAGE
!
DISCONNECT ALL SOURCES OF POWER (AC AND DC) BEFORE INSTALLING OR REMOVING
ANY MODULES OR WIRING. THE PANEL AND ASSOCIATED EQUIPMENT MAY BE DAMAGED
BY REMOVING AND/OR INSERTING CARDS,MODULES OR INTERCONNECTING CABLES
WHILE THIS UNIT IS ENERGIZED.
Primary Power Source (AC) and Earth Ground Connections
AC power connections are made inside the control panel cabinet. The primary power source for the
panel is 120 VAC, 60 Hz, 3.66 amps for the RP-2002/C or 240 VAC, 50/60 HZ, 2.085 amps for the
RP-2002E. Run a pair of wires (with ground conductor) from the protected premises main breaker
box to the AC terminal block TB1 on the main power supply. As per the National Electrical Code,
use 14 AWG (2.00 mm
equipment may be connected to this circuit. In addition, this circuit must be provided with overcur-
rent protection and may not contain any power disconnect devices. A separate Earth Ground con-
nection must be made to ensure proper panel operation and lightning and transient protection.
Connect the Earth Ground wire [minimum 14 AWG (2.00 mm
box and then run wire to TB1. Do not use conduit for the Earth Ground connection since this does
not provide reliable protection.
Secondary Power Source (Batteries)
Observe polarity when connecting the battery. Connect the battery cable to J12 on the main circuit
board using the plug-in connector and cable provided. The battery charger is current-limited and
capable of charging sealed lead acid batteries. The charger shuts off when the system is in alarm.
WARNING: RISK OF PERSONAL INJURY
!
BATTERY CONTAINS SULFURIC ACID WHICH CAN CAUSE SEVERE BURNS TO THE SKIN
AND EYES AND CAN DESTROY FABRICS. IF CONTACT IS MADE WITH SULFURIC ACID,
IMMEDIATELY FLUSH THE SKIN OR EYES WITH WATER FOR 15 MINUTES AND SEEK IMMEDI-
ATE MEDICAL ATTENTION.
120 VAC Power
Neutral (L2)
Ground Stud
RP-2002 Series Manual — P/N 53039:E6 1/26/2017
2
, 1.6 mm O.D.) or heavier gauge wire with 600V insulation. No other
Hot (L1)
Ground
J12
Figure 2.4 Operating Power Connections
2
)] to the grounding stud in the back-
-
+
Batteries
Installation
23