Installation frame E4 is suitable for:
● Instalaci on solid wall/ceiling construction
● Instalaci outside solid ceiling constructions with concrete
On the inside is installation frame equipped by intumescent sealing. It enlarges its capacity and air
proofs the gap between installation frame and damper body.
● Gypsum wall construction has to be installed according manufacture requirements.
● Installation frame:
● Fasteners:
● a x b = (A + 5 mm) x (B + 5 mm)
● a x b = (A + 100 mm) x (B + 100 mm) installation with concrete
cement lime plates
galvanized plate
150*
max. 750
150*
POSITION:
1
Fire damper FDMB with installation frame E4
2
Fitting with threaded rods or steel bracket
3
Concrete B20
4
Rebar
74
max. 100
* min. 110 - Concrete/ min. 125 - Aerated concrete