44 Installation checklist
Safety
DANGER
High voltage!
Obey the instructions in chapter
or damage to the equipment can occur.
Before starting to work on the drive, make sure:
that the main and auxiliary power supply to the drive is switched off, locked out, and
tagged out.
that bypass - drive is in non-operating state and after de-energizing.
that safety ground connections are in place for both input and output terminals of
converter.
that personal protective equipment is provided and used when required.
that everyone involved is informed.
Before energizing the drive, make sure:
that all foreign objects are removed from the drive.
that all internal and external covers are securely fastened and all doors are closed,
locked and / or bolted.
that the release dials of safety switches are in the locked position.
WARNING! Obey the instructions in chapter
them, injury or death, or damage to the equipment can occur.

Checklist

Do the steps in section
work. Go through the checklist together with another person.
Mechanical installation
1.
Ambient operating conditions meet the specifications given in chapter ACS580MV hardware
manual.
2.
Drive installed according to the instructions in this manual (Chapters
Electrical
installation).
3.
Drive securely fastened to the floor.
4.
Fan units installed.
Safety instructions
Precautions before electrical work
. If you ignore them, injury or death,
Safety instructions
on page
15
before you start the
Mechanical installation
. If you ignore
and