Receiving And Handling

After the machine has been uncrated, examine the
case sealer for damage that might have occurred
during transit. If damage is evident, file a damage
claim immediately with the transportation company
and also notify your 3M Representative.

Machine Set-Up

Important – Read "Warnings", on page 20,
before attempting to set-up the case sealer
for operation.
It is recommended that the case sealer be set-up
and operated with product before placing it in the
production line. This approach will allow your
thorough review and familiarization with the case
sealer before subjecting it and operating personnel
to a production situation where time for set-up,
adjustments, and operator training usually becomes
limited.
For future reference, record machine serial number
on front cover of this manual in the space provided.
The following instructions are presented in the order
recommended for setting up and installing the case
sealer, as well as for learning the operating
functions and adjustments. Following them step
by step will result in your thorough understanding of
the machine and an installation in your production
line that best utilizes the many features built into the
case sealer. Refer to Figure 3-1 and 3-2 to identify
the various components of the case sealer.
Note – A tool kit consisting of metric open
end and hex socket wrenches is provided
with the machine. These tools should be
adequate to set-up the machine, however,
other tools supplied by the customer will be
required for machine maintenance.

PACKAGING AND SEPARATE PARTS

1. Follow "Unpacking Instructions" label attached
to corrugated packing cover.
2. Height adjustment crank is shipped in upside
down position. Remove the crank and install
right side up as shown in Figure 2-1A.
Note: Height adjustment crank can be
installed on either column for operator
convenience.
3. Cut and remove tie down straps that secure
upper assembly to machine bed on each side of
machine at vertical columns.
4. Crank the upper assembly up and remove the
2 x 4 wood frame that supports the flap folder
assembly.
5. Secure pneumatic controls to side frame as
shown in Figure 2-1B.
6. Install the tape drum bracket on the upper taping
head as shown in Figure 2-1C.
7. Hold taping head BUFFING ROLLER and cut
and remove cable tie that holds applying/buffing
arms retracted on both taping heads. See
Figure 2-1D. Allow buffing/applying arms to
extend slowly. Also cut and remove cable ties
that secure lower taping head in place.
WARNING – Follow this step
carefully as spring pressure is
applied to applying and buffing arms when
cable tie is removed. Keep hands/fingers
away from tape cut-off knife under orange
knife guard. Knife is extremely sharp and
can cause severe injury.
8. Push buffing roller into head to check for free,
smooth action of upper and lower taping heads.
WARNING – Keep hands/fingers
away from tape cut-off knife under
orange knife guard. Knife is extremely
sharp and can cause severe injury.
11

Advertisement

Table of Contents
loading

Table of Contents