5. INSTALATION

5.1.

RECEPTION OF GOODS

Each device is carefully checked before transportation. When receiving the goods, checking the devices for any damage made during transporta-
tion is recommended. If any damage to the unit is observed, immediately contact the representatives of a transport company. Please inform the
representative of the manufacturer, if any deviation of the device is noticed.
5.2.

TRANSPORTATION AND STORAGE

• All units are factory-packaged to withstand normal conditions of transportation.
• When unpacking, check the unit for any damage made during transportation. Installing of damaged units is not allowed!
• The packaging is used for protection purpose only!
• When unloading and storing the units, use suitable lifting equipment to avoid damage and injuries. Do not lift units by holding on power supply
cables, connection boxes, air extract or exhaust flanges. Avoid hits and shock overloads. Before installation, the units must be stored in a dry
room with the relative air humidity not exceeding 70% (at +20°C) and with an average ambient temperature ranging between +5 °C and +30 °C.
The storage place must be protected against dirt and water.
• The units must be transported to the storage place or installation site using forklifts.
• The recommended storage i period should not be longer than one year. In case of storing the units for a period longer than one year, checking
if the fan bearings and motor rotate without difficulty (turning the impeller by hand) and if the electric circuit insulation is not damaged or the
moisture has not accumulated must be performed before the installation of the unit.
SMARTY
2 XV
3 XV
4 XV F2
In order to prevent damage to the casing, only a product placed on a pallet should be lifted.
5.3.

UNPACKING

Accessories may be packed together with the product. Prior to transporting the unit, the accessories should be unpacked
first.
• Remove the film from the unit.
• Remove the bracing packaging tape that keeps the protective profiles in place.
• Remove the protective profiles.
• After unpacking the unit, examine it to make sure that no damage was made during transportation. Installing of damaged units is not allowed!
• Before commencing the installation of the unit, please check if all ordered equipment have been delivered. Any variation from the ordered equip-
ment list must be reported to the product supplier.
SMARTY XV v2020.3
W
H
W
[mm]
[mm]
2160
700
1060
730
1060
730
Figure 5.2.1. Lifting by forklift.
H
L
L
Max. number of transported
packages
[mm]
800
585
585
[pcs.]
6
1
1