Sequence For Installing The Power Module - Siemens SINAMICS G120 Installation Manual

Power modules, ip20 / push-through technology (pt)
Hide thumbs Also See for SINAMICS G120:
Table of Contents

Advertisement

Installing
3.4 Mounting the Power Modules
3.4.1

Sequence for installing the Power Module

During installation, comply with the sequence listed below.
Frame sizes FSA ... FSC
1. Prepare the cabinet.
2. Mount the shield plates.
3. Install the Power Module.
4. If you are using a Brake Relay or Safe Brake Relay:
Install the Brake Relay next to the converter.
Frame sizes FSD ... FSG
1. Prepare the cabinet.
2. If you are using a Brake Relay or Safe Brake Relay:
Install the Brake Relay on the rear side of the shield plate.
3. Mount the shield plates.
4. Install the Power Module.
30
Hardware Installation Manual, 01/2020, A5E33294624B AL
Power Module PM240-2