3.10 Commissioning report

The boiler can be operated with a gas or dual fuel burner.
− Carefully complete the commissioning report for the relevant approved burner.
− Sign all completed commissioning work and enter the date.
COMMISSIONING STEPS
Flush the heating system.
Fill the heating system with water.
Vent the heating system.
Carry out tightness test.
Switch on the control unit.
-Boiler-specific parameters set and recorded.
Ensure the function of all safety equipment.
Check the fuel line for tightness.
Start the burner.
Complete the burner test report regarding the individual output
Conduct a tightness test on the hot gas side.
After a short time in operation, tighten the screws in the com-
bustion chamber door to prevent leakage around the door as a
result of the packing cord settling.
Check the flange connections and fittings after the boiler has
been heated up and retighten.
Check flue path for tightness.
Check the flue gas temperature.
Carry out a function test on all safety equipment and record
Instruct the system user and hand over technical documenta-
Enter the fuel used in the table
(See "General" operating instructions)
Confirm commissioning by a competent person.
Company stamp/signature/date
stages.
this.
tion.
COMMENTS (SIGNATURE)