Parallel Connection; Mechanical Installation; Module Mounting; Site Consideration - LG M1C Series Installation Instructions Manual

Power modules
Table of Contents

Advertisement

- Parallel Connection

The solar modules may be combined in parallel to produce the desired current output.
Every series string or solar module must be fused prior to combining with other strings. By pass diodes
are factory installated in the solar modules. Please refer to the applicable regional and local codes for
additional fusing requirements and limitations on the maximum number of solar modules in parallel.
* Maximum parallel strings without proper measures [e.g. fuse (15A) and/or bloking diode]
: 1 string
[Parallel configuration is not limited if proper measures are taken to block the reverse current flow,
e.g. fuses for the protection of the module and cables from over-current and/or bloking diodes for
prevention of unbalanced string voltage].

5. Mechanical Installation

- Module Mounting

The LG Electronics (LGE) Limited Warranty for solar modules is contingent upon modules being mount-
ed in accordance with the requirements described in this section.
* Application class A

- Site Consideration

LGE solar modules should be mounted in a location that meets the following requirements.
Operating Temperature
All LGE solar modules must be mounted in an environment that ensures that the LGE solar module will
operate within the following maximum and minimum operating temperatures.
Maximum Operating Temperature
Minimum Operating Temperature
Care should be taken to provide adequate ventilation behind the solar modules, especially in hot envi-
ronments.
- PARALLEL for more voltage -
+90°C (194°F)
-40°C (-40°F)