4.1 Separator commissioning
Before the separator is put into service please make sure that:
- The separator is completely clean, including inlet and outlet,
and that the interior of the chamber is free of dirt and debris.
- The cleaned separator is completely filled with clean cold
water up to the outlet.
4.2 Commissioning participants
The commissioning of the separator is usually handled by a tra-
desman although this can be handled by a KESSEL contractor
or KESSEL employee if desired.
1) The following people should be on hand during the commis-
sioning:
- Building contractor representative
- Plumber / tradesman who will be maintaining the separator
- Building maintenance personnel
- Disposal company who will be handling the disposal account
The first emptying (disposal) of the separator contents should
take place within 2 to 3 weeks from the day the separator was
placed into service.
Disposal intervals
According to DIN V 4040-2, it is advised that sludge and grease
separators should be fully emptied, cleaned and refilled with
cold fresh water at fourteen day intervals or at least on a month-
ly basis. In order for a grease separator to function as designed,
it is very important that the separator is emptied at regular in-
tervals as described above. Due to this, it is recommended that
a licensed disposal company is contracted to empty the sepa-
rator at regular intervals and during times when strong odours
will not present a problem. During disposal of DIN 4040 under-
ground grease separators, first the grease separation compart-
ment must be emptied and than the sludge compartment. This
prevents any flotation of integrated sludge compartment.
4. Commissioning
5. Separator contents disposal
29
2) Commissioning preparation
- Separator is completely filled with clean water
3) Commissioning
- Separator to be checked for watertightness and for proper
functionality
- Contents of this user's manuals to be discussed with those
present
4) Transfer of this manual to the appropriate personnel
4.3 Handover certificate
Disposal procedure
• Remove manhole cover.
• Place disposal truck's suction hose inside separator and re-
move entire contects of chamber. CAUTION: Dispose the
Grease Separation area first and then the sludge trap.
• Rinse and clean interior walls of chamber.
Remove coagulated fat/oil and debris.
• Refill chamber with cold clean water. CAUTION: Fill first the
sludge trap than the grease separation area.
• Clean and grease all accessible seals. Replace seals if ne-
cessary.
• Replace cover(s) and secure with cover clamps.