Instantaneous water heater system WM 400 V

7 Initial operation

7.1 Connection assignment to the personal lock system Quick-Dush
 Establish the current supply of the water management (400V, 32A 3+N+PE)
 Establish the fresh water supply of the water management to the connection "fresh
water filling".
 Establish connection "warm water exit" with the shower roof element
 Establish connection "sewage water suction" with the shower floor element
 Connect the drain hose connection with "waste water" and sewer

7.2 Preparing for operation

 Open fresh water intake
 Fill the sewage pump (see chapter 8.2 )
 Set the temperature of shower water at the thermostat
 Set the main switch to „ON"
 The system is now operational
Note:
Before the start up of the sewage pump, it is to verify whether the shaft can be turned by
hand. On this purpose a screwdriver has to be put in the notch on the shaft extension of
the fan side and move the shaft. With new pumps, the strong initial rotational resistance
of the wheel will come loose after running.