STEP 1: Floor plan and
compass
STEP 2: Draw relevant
RF shielding on the
floor plan
78 / 84
Siemens
Building Technologies
14.6 Range planning
RF range is typically limited by fire protection walls that are considered shielding.
Within fire protection areas, light walls or glass partitions with solid RF properties
are often used. Avoid metal reinforcement or metalized glass!.
The following diagrams illustrate how to implement a reliable RF plan in three
steps.
Fire protection walls
Elevator shafts, stairwells and other supply areas
Desigo TRA Engineering, mounting and installation
EnOcean RF networks
CM111043en_09
2016-02-22