Bacnet - Siemens Climatix Series Basis Document

Hide thumbs Also See for Climatix Series:
Table of Contents

Advertisement

Devices
Tools
Illustration
Prerequisite
Commission BACnet/IP
module
128 / 244
Basis Document Siemens Climatix Control System
Siemens
Page 128
BDCX.100820.01GB
Building Technologies
9.4

BACnet

9.4.1
Commission the BACnet/IP module
Participating devices
− Climatix controller POL6XX.
− Communication module POL908.
Participating tools:
− Operator unit (HMI).
− PC with web browser.
PC
SCOPE
WEB
The SAPRO application (MBRCode.bin) is fully commissioned.
The BACnet/IP module is connected to the bus and configured. Procedure:
Step
Action
1
Controller OFF.
2
Connect BACnet/IP module to the controller via plug connection.
3
Connect the BACnet/IP bus cable to the module.
4
Controller ON:
 The module starts / initialization begins.
 As soon as the two LEDs "BSP" and "BUS" are steady green, com-
munication with the controller and bus (BACnet) is active.
Caution:
HMI must be reset a second time to update; prior to parameterization.
5
Enter BACnet settings via HMI and web browser.
6
Configure BACnet/IP module.
Standard application AHU
Communication
BACnet / Ethernet IP
POL908 / POL6XX
P3933Z27
HMI
CE1P3977en_02
01.02.2010