Installation
3.2 System Installation
Installation
1. Disconnected all power supplies to the system and wait 5 minutes.
2. Remove the Power Module (PM).
3. Remove the blank plate from the side of the terminal housing.
4. Remove the Control Module (CM).
5. Fit the 24V PSU to the side of the terminal housing, ensuring that no cables or wiring are
trapped between the 24V PSU and the terminal housing. Tightening torque: 1.5 Nm.
6. Connect the input cable to the DC link terminals in the terminal housing (black to DC- and
red to DC+).
7. The 4-way 24V cable is routed underneath and then over the top of the CM.
8. Fit the 4-way connector as shown in the illustration below.
9. Fit the CM back into place - ensuring that it securely fastened into place.
10.Replace the PM.
11.Fit blanking cap to the 7/8th connector.
12.Power can now be restored to the system.
Figure 3-6
Fitting the input and output connections
48
SINAMICS G110M Getting Started
Getting Started, 09/2014, FW V4.7, A5E31298643B AC