Mitsubishi Electric A960GOT User Manual page 56

Human machine interface, graphical operator terminal
Table of Contents

Advertisement

6 HANDLING
GOT side
6 - 9
3) For other cables between GOT and GOT
• Wind cable shield material around the cable, and pull out the
grounding braided wire of the cable shield material with the length
shown below.
• Do not pass the grounding braided wire on the programmable logic
controller through the core.
GOT side
(ZCAT3035-1330)
Cable shield material
130
Grounding braided
(5.12)
wire(50mm(1.97inch))
Within 150
(5.90)
b) CPU Direct connection
1) For RS-232C cable (QC30R2)
• Peel the sheath (with the length shown below) at both ends of the
cable, and expose the shield braided wire for grounding.
GOT side
(ZCAT3035-1330)
130
(5.12)
Within 230
40
(9.06)
(1.57)
2) RS-422 cable (For AC30/100/300R4-25P)
For A985GOT
• Wind cable shield material around the cable, and pull out the
grounding braided wire of the cable shield material with the length
shown below.
• Do not pass the braided wire for grounding through the ZCAT2436-
1330 ferrite core.
Ferrite Core
(ZCAT2436-1330)
150
(5.90)
Ferrite Core
Within 150
(5.90)
Ferrite Core
PLC side
40
Within 300
(11.81)
(1.57)
Ferrite Core
(ZCAT2436-1330)
(ZCAT3035-1330)
Cable shield material
Grounding braided
wire(200mm(7.87inch))
MELSEC-GOT
GOT side
130
(5.12)
Unit : mm (inch)
130
(5.12)
Unit : mm (inch)
Ferrite Core
PLC side
150
(5.90)
Unit : mm (inch)
6 - 9

Hide quick links:

Advertisement

Table of Contents
loading

This manual is also suitable for:

A970gotA975gotA985got

Table of Contents