The "Launch Configuration Selection" screen appears on and after the second operation of the step 2.
Select "Launch the selected launch configuration", and click the [OK] button.
■Debugging the user program
Operating procedure
1.
Select the created project in the "Project Explorer" window, and click the [] button on the right side of
2.
Select [Debug Configurations].
The "Debug Configurations" screen appears.
3.
Select the downloaded module "R12_SampleProject.out" under "VxWorks Kernel Task".