Commissioning; Prior To Commissioning - Siemens SIMOTICS HV C Operating And Installation Instructions

Induction motor
Table of Contents

Advertisement

Commissioning

Observe the following when carrying out any work on the machine:
● Comply with the general safety instructions (Page 13)
● Comply with the applicable national and sector-specific regulations.
● When using the machine within the European Union, comply with the specifications laid
Note
Service Center
Please contact the Service Center (Page 111) if you require commissioning support.
7.1

Prior to commissioning

Once the system has been correctly installed, you should check the following prior to
commissioning:
Note
Checks to be carried out prior to commissioning
The following list of checks to be performed prior to commissioning does not claim to be
complete. It may be necessary to perform further checks and tests in accordance with the
specific situation on-site.
● The machine is undamaged.
● The machine has been correctly installed and aligned, the transmission elements are
● All fixing screws, connection elements, and electrical connections have been tightened to
● The operating conditions match the data provided in accordance with the technical
● Moving parts such as the coupling move freely.
● All touch protection measures for moving and live parts have been taken.
Electrical connection
● The grounding and equipotential bonding connections have been made correctly.
● The machine is connected so that it rotates in the direction specified.
SIMOTICS HV C 1NB1402-2AA84-4CA0-Z
Operating Instructions 06/2018
down in EN 50110‑1 regarding safe operation of electrical equipment.
correctly balanced and adjusted.
the specified tightening torques.
documentation, such as degree of protection, ambient temperature, etc..
7
69

Hide quick links:

Advertisement

Table of Contents
loading

This manual is also suitable for:

1nb1402-2aa84-4ca0-z

Table of Contents