Plug the pump into AC wall outlet.
Battery Operation
Unplugging the pump from the AC line will place the pump on battery power. To recharge the
battery, plug the pump into an AC wall outlet. Pump will automatically begin charging.
Programming
-These general instructions are for inserting the Kangaroo 924 Feeding Sets into
the Kangaroo 924 Feeding Pump.
1. Close roller clamp on pump set.
2. Fill feeding bag or spike container prior to setting up pump.
3. In order to achieve proper accuracy, the fluid line in the feeding bag must be 28 inches
above the top of the feeding pump when initiating the feeding cycle.
4. Slowly open control clamp and fill entire line with fluid, leaving a few drops of fluid in the drip
chamber.
NOTE: Avoid filling the drip chamber more than half full.
5. Close roller clamp.
6. Load set per arrow diagram on pump. Do not overstretch tubing.
7. Press
and wait while pump performs a system check.
ON
8. Check VOL CLR light or press VOL then VOL CLR to clear volume.
9. Set feed rate using one of the two following options:
• Pressing the increase
• Turning the knob on the left side of the pump
Setting the Volume to be Delivered "VTBD" Rate (optional feature)
• Press the VTBD button.
• S et "VTBD" by using knob on side of pump, or by pressing the increase
button.
• O nly use the "VTBD" option if you want the pump to stop and alarm once a set amount of
formula is delivered.
10 . Open roller clamp.
11. Press START/HOLD .
To Change Rate:
1. Press
START
.
HOLD
2. Set new rate by pressing the
3. Press
.
START
HOLD
See pump operating manual for detailed instructions.
924 Enteral Feeding Pump
or
decrease button, or
START
HOLD
or
keys on the front panel.
or
decrease
Need help?
Do you have a question about the Kangaroo 924 and is the answer not in the manual?
Questions and answers