7SR18 Commissioning & Maintenance Guide
Section 5: Control & Logic Functions
5.1
Q
L
UICK
OGIC
If this functionality is used, the logic equations may interfere with testing of other protection functions in the relay.
The function of the Quick Logic equations should be tested conjunctively with connected plant or by simulation to
assess suitability and check for correct operation on an individual basis with tests specifically devised to suit the
particular application.