Installation - Siemens Milltronics MILLFLO Instruction Manual

Table of Contents

Advertisement

Installation

1.
Set the Millflo housing in place ensuring that the flowguide and outlet gaskets are
correctly located.
2.
The housing must be vertical within 1° in two planes 90° apart.
3.
Bolt the flowguide and outlet flanges to the process piping.
4.
If the load cell/sensing plate assembly was not removed prior to beginning the
installation procedure, the shipping stop must be removed. Refer to
page 7 to remove the shipping stop.
If the load cell/sensing plate assembly was removed, reverse the disassembly
procedure to reassemble the load cell/sensing assembly into the housing and to
replace the cover/junction box assembly on to the top access flange. Do not reinstall
the shipping stop. Exercise caution while handling the load cell/sensing plate
assembly. Refer to the diagrams in the
5.
Wire the unit in accordance with Siemens Milltronics supplied connection diagrams
or as described in the integrator instruction manual.
(2)
NOTE: All items other than Millflo supplied by customer
Page 8
Milltronics Millflo – INSTRUCTION MANUAL
Load Cell Handling
section on page 6.
Millflo
mounting hardware
(1) gasket
(3) outfeed pipe
Disassembly
on
(3) infeed pipe
mounting hardware
(1) gasket
7ML19985CS01