Control Bus Cable Location - GE TLE series 600 User Manual

600 and 800 kva 400vac ce s1
Table of Contents

Advertisement

5.10.3 Control bus cable location

WARNING !
This installation must be verified by trained personnel before the initial start-up.
ENSURE THAT THE UPS INSTALLATION IS COMPLETELY POWERED DOWN.
Fig. 5.10.3-1 TLE Series 600
View electronic module on intermediate unit
Access to the control bus connection
The communication bus cable connectors are placed on the two boards "P13/P14 – IM0222 – Bus
Interface Board" (see Fig. 5.10.3-1 and 5.10.3-2).
J1B/2÷5
J1B/1
J1A/2÷5
J1A/1
Fig. 5.10.3-3 View electronic module on intermediate unit
Modifications reserved
GE_UPS_OPM_TLE_SCE_M60_M80_1GB_V020.docx
Critical Power
Q1
J1
B
J2
J1
A
J2
Fig. 5.10.3-2 TLE Series 800
View electronic module on intermediate unit
Control bus cables connection
Plug the cables J1A – J2A (1/2/3/4/5) and J1B –
J2B (1/2/3/4/5) on the connectors J1A – J2A
and J1B – J2B placed on the two boards
"P13/P14 – IM0222 – Bus Interface Board".
Fix the communication bus cables J1A – J2A
(1/2/3/4/5) and J1B – J2B (1/2/3/4/5) with the
provided cable clamps "A".