Documentation of the inverter
The following must be documented for the inverter:
● The results of the acceptance test.
● The settings of the integrated drive safety functions.
The STARTER commissioning tool logs the settings of the integrated drive functions, if
necessary.
The documentation must be signed.
Who may perform the acceptance test of the inverter?
Personnel from the machine manufacturer, who, on account of their technical qualifications
and knowledge of the safety functions, are in a position to perform the acceptance test in the
correct manner are authorized to perform the acceptance testing of the inverter.
Reduced acceptance test after function expansions
A full acceptance test is necessary only after first commissioning. A reduced acceptance test
is sufficient when safety functions are expanded.
Measure
Functional expansion of the ma-
chine (additional drive).
Transfer of inverter settings to
other identical machines by means
of series commissioning.
Document for the acceptance
The STARTER provides you with a number of documents to be regarded as a
recommendation for the acceptance tests of the safety functions.
Distributed converter for SIMOGEAR geared motors
Operating Instructions, 09/2017, FW V4.7.9, A5E31298649B AH
Acceptance - completion of commissioning (Page 210)
6.13 Safe Torque Off (STO) safety function
Acceptance test
Acceptance test
Documentation
Yes.
Only check the safety
functions of the new
drive.
No.
Only check the control
of all of the safety
functions.
Advanced commissioning
Supplement machine overview
Supplement inverter data
Add function table
Log the new checksums
Countersignature
Add machine description
Check checksums
Check firmware versions