2 Install the e2695 Separations Module
Major steps to installing the separations module:
Obtain required
materials
Review site
requirements
Unpack and
inspect parts
Connect power
cables
Required materials:
Screwdriver, #2 Phillips
Screwdriver, flat-blade
Open-end wrench, 5/16-inch
Tubing cutter
e2695 Separations Module Startup Kit
Once you install the separations module, proceed to

Site requirements

The installation site must meet the specifications in the following table.
46
July 29, 2013, 715003794 Rev. B
Connect tubing
Connect signal
cables
Install hardware
options
Installation
complete
®